In 2004, Advanced Products Co. had about $2 billion in annual revenue. Twenty years later, it was down to about $360 million. To grow again, leadership needed to fix the business, and it started with production.
Some of the company's nine global factories were running below capacity, so the answer looked obvious. Close the high-cost U.S. plant, move its volume to a cheaper plant offshore, and run the remaining factories fuller.
The cost math held up. Nobody had worked out what the move would do to customers. Many West Coast customers were used to getting orders the day after they placed them, because the U.S. plant was close by. After the move, the same orders took at least three to five days, and nobody had warned them. A decision meant to make the company more efficient disrupted the operations of a big share of its customers.
I don't think leadership made a bad call on the information in front of it. The problem was how the decision was defined. It was treated as a manufacturing project when it was really a change to how the whole business served its customers.
In Decipher & Deliver, I compare a company that needs transformation to an old house with leaky pipes. Years of fast growth get handled one repair at a time. The system still works, just not well. Fix one leak and the pressure moves to the next weak joint. Advanced Products Co. fixed its capacity problem, and the pressure moved to customer lead times.
Friction is any place where one part of the business depends on another, so a change in one causes trouble in the next. Finding it is the first job. Here, the friction point was the link between where products were made and how fast customers got them. Nobody mapped it before the decision, so the company found it after the customers did.
Bain & Company's 2024 research found that only 12% of companies achieve their original transformation ambitions. One common cause appears before any work begins. A change that crosses functions gets planned and staffed like a single-department project.
Every transformation is a change, but most changes aren't transformations. A change project is usually limited to one function and can be run by the people who already own that work. A transformation crosses functions; asks the company to do things it can't do yet and needs more planning and oversight.
When companies first come to us at Quadrillion Partners, they often aren't sure which one they're dealing with. We check the plan against four questions.
This is the question that finds the friction. The more departments and customer groups a change reaches, the more it behaves like a transformation and the more risk it carries. Advanced Products Co. judged its closure on manufacturing cost, but production and delivery were tied together, so the plan needed both. Before approving the work, list every function and customer group it affects and where they depend on the same process or system. Then put those dependencies in the plan.
If the team doesn't have the experience, skills, or tools to carry the change across departments, you're in transformation territory. Assigning someone the outcome doesn't give them the capability. Name what the company has to be able to do that it can't do reliably now and decide who will build it and own it.
A large jump in revenue or profit, a new market or a redesigned operating model takes more time, people and capital. It also carries more execution risk, and bets that size usually go to the board. Weigh the expected return against what it will take to deliver and compare it with the other bets competing for the same money.
If the work needs a business case, milestones, financial goals and a monthly review, it's a transformation. Too many programs get that attention once, at approval, and then run on autopilot. A team can finish every task on the plan and still miss the result the plan was approved for. Monthly reviews against that result show you the gap while there's still time to close it.
Labeling something a transformation changes how the work is run. It doesn't have to change how big the work is. It gets its own goals, a plan for the capabilities it's missing and oversight that continues after approval. Sometimes a small fix turns out to be the symptom of a bigger bottleneck. When that happens, resize the plan instead of forcing the bigger problem into the smaller project.
Before you approve the next one
1 - List every function and customer group the change affects, and where they depend on each other.
2 - Name the capabilities you don't have yet and who will build them.
3 - Weigh the return against the cost to deliver and the other bets competing for the same capital.
4 - Put a monthly review on the calendar, measured against the result the plan promised.
When Advanced Products Co. considered closing another factory, it brought us in to map the dependencies first. Over six weeks we ran about 35 factory and supply chain simulations, testing each closure scenario against cost, bottlenecks and customer delivery times. The company closed one factory and moved its volume to the others without hurting customer deliveries.
The decision was the same. This time it was planned as a transformation.
I go further on each of these questions, and on how to run a transformation once it's approved, in Decipher & Deliver: Removing Friction Points in Business and Digital Transformations.